For Example: Risk Management

The form serves to assess the risks in the project. The risks and their importance are in the template (shaded). These are actual consulting project risks as identified by consulting industry researchers. Again, a detailed procedure guides through the process of filling in the details. An example could look like this:

Customising and adapting the templates
Customising and adapting the templates

Gaia Project Plan Risk Management Original Rev. 1 Rev. 2
Date
Approved

Risk

Importance Mitigation Strategy Exposure ($) Risk Potential (%)
Executive related Risks
Executive Management Support 16 / 100

N/A

0%
Ownership 6 / 100

N/A

0%
Clear Vision & Objectives 3 / 100 1.Management Meeting

2.Work Shop

80%
Clear Statement of Requirements

15 / 100

TBA 50%
Realistic Expectations

10 / 100

Present. Proj. Mgr. 50%
Project Management Risks
Proper Project Mgmt & Planning 11 / 100 TBA

60%

Smaller Project Milestones 9 / 100 TBA

60%

Competent & Focused Staff

11 / 100

TBA 20%
User related Risks
User Involvement & Participation 19 / 100 Change Managem’t 80%

An example for Project Plan Integrity
An example for Project Plan Integrity

This example for Mitigation Strategies relates to the example in the Risk Management table above. The purpose of this template is to instigate and control the execution of the mitigation strategies, which will trigger entries into the Project Schedule and Resource Plan.

Risk Mitigation Strategy

(brief description)

Action by Review of effect Activity and Review in Schedule Activity and Review Resourced
Clear Vision & Objectives Management Meeting to convey CEO’ Vision and obtain feedback (17.3.2001) Steering Committee 22.3.01 No No
Clear Vision & Objectives Work shop with project team and seconded staff (18.3.2001) PM & Steering Committee. 22.3.01 No No
Clear Statement of Requirements TBA No No
Realistic Expectations Presentation Project Manager of potential, past projects and results (19.3.2001) PM 22.3.01

No

No
Proper Project Mgmt & Planning TBA TBA
Smaller Project Milestones TBA TBA
Competent & Focused Staff None 22.3.01

No

No
User Involvement & Participation Set up Change Management. Plan, agree and instigate activities. (16.3.2001) Steering Committee

9.4.01

No No
User Involvement & Participation Instigate User Group. Develop topics, tactics, activities, membership (17.3.2001)

PM

9.4.01 No No